HNBESS 261 kWh battery cabinet standing in a workshop test bay

FAMILY 12 · HIGH-VOLTAGE CABINET · 3 BUILDS

261 kWh High-Voltage Battery Cabinet, Air or Liquid Cooled

A complete unit with the PCS inside, delivering three-phase 380V at its terminals. 261 kWh of LFP at 832V, 100 or 125 kW. The air-cooled builds also accept up to 250 kW of PV directly.

261 kWh

Nominal, 13 packs of 314Ah

125 kW

Rated AC output, 137.5 kW peak

832 V

DC bus, 650 to 949V window

2.1 t

Air cooled, 2.6 t liquid

WHO THIS IS FOR

A cabinet that arrives as a plant, not as parts

This is the size where the project starts to matter. It suits a cold store running peak shaving, a fuel station with a variable load, or a factory fighting a demand charge it cannot control. The cabinet lands with the PCS, the BMS, the cooling and the communication stack already inside, so the site work is a foundation, four cables and a network drop.

It is not for a container-scale utility job. Above roughly 500 kWh, look at the container family, where the battery ships without a PCS and the design work sits with your EPC.

HNBESS 261 kWh air-cooled battery cabinet with dual doors and vent panels

Air-cooled build: 1,260 mm wide, 1,980 mm tall, two doors, 2,100 kg.

THREE BUILDS

Same battery, three different machines

The energy is identical on all three. What changes is how the heat leaves, how the fire is handled, and whether the unit accepts PV. Those three differences decide which one your site can actually take.

Build Cooling AC power Weight Dimensions W × D × H Fire suppression
261 kWh / 100 kWAir100 kW2,100 kg1,260 × 1,420 × 1,980 mmOptional, specified at order
261 kWh / 125 kWAir125 kW2,100 kg1,260 × 1,420 × 1,980 mmOptional, specified at order
261 kWh / 125 kW liquidLiquid125 kWAbout 2,600 kg1,000 × 1,300 × 2,500 mmBuilt in at factory

All three run 1P260S at 832V with 200A maximum charge and discharge. The liquid-cooled cabinet is 260 mm narrower but 520 mm taller, which changes the door height you need, not just the floor area.

AIR OR LIQUID

The decision that changes the site work

This is not a preference. Air and liquid cabinets need different foundations, different clearances and different approval paperwork.

Air cooled Liquid cooled
SuppressionOptional at order. Skip it and you own the decision at approvalPerfluorohexanone, aerosol and water suppression, factory fitted
DetectionCell level through the BMSTemperature, smoke and CO sensors, independent of the BMS
EnclosureIP54, whole cabinetIP65 battery bay, IP54 electrical bay
PV inputUp to 250 kW on 8 trackers, or 200 kW on 10Not listed in the catalogue. Confirm before you design around it
NoiseNot published75 dB or less
Ambient limitRated to 60 °CRated to 50 °C, derated above 45 °C
AltitudeNot publishedBelow 2,000 m, derating above
CommunicationRS485, CAN, EthernetCAN and Ethernet, Modbus TCP or RTU
Best forShaded plant room, temperate site, PV coupledOutdoor pad, hot climate, fire authority wants factory suppression
HNBESS 261 kWh liquid-cooled battery cabinet with a taller narrower frame

Liquid-cooled build: narrower at 1,000 mm, taller at 2,500 mm, about 2,600 kg.

Why the liquid unit costs more and still wins the order

It arrives with suppression and detection already inside. That means one less item on your procurement list, one less interface for the fire consultant to review, and a datasheet that answers the question an inspector is about to ask.

On the air-cooled cabinet you specify suppression at order. Do that, and the gap narrows. Skip it because the budget was tight, and you are explaining the omission six months later to someone with a clipboard.

PV AND GRID

Up to 250 kW of panels, straight into the cabinet

The air-cooled builds carry their own MPPT trackers, which means the panels land on the cabinet and no separate PV inverter is needed. On the 125 kW build there are 8 trackers, on the 100 kW build there are 10.

Parameter261 kWh / 100 kW261 kWh / 125 kW
Max PV input power200 kW250 kW
Max PV voltage1,000 V1,000 V
MPPT window150 to 850 V150 to 850 V
MPPT trackers108
Max efficiency98.70%98.70%
System efficiency88% or better88% or better
Grid connectionThree-phase four-wire, 380V, 340 to 460V toleranceThree-phase four-wire, 380V, 340 to 460V tolerance
Off-grid output380V, 50 or 60 Hz380V, 50 or 60 Hz
The liquid-cooled build has no PV figures in the catalogue. It is documented with DC and AC parameters only. If your design depends on connecting panels straight to that cabinet, ask us in writing before you commit, because we will not assume the trackers are there.

HOW IT IS BUILT

Inside the cabinet

Interior of an HNBESS battery cabinet showing pack racks and busbars

Thirteen 64V packs on rack shelves, copper busbar down each side, BMS in the upper bay.

  • Thirteen packs, 1P260S. Each pack is 64V at 314Ah, wired in series to 832V. Replace one pack at a time rather than the whole string.
  • Copper busbar, not cable. The DC path is solid busbar on both sides of the rack, which keeps the voltage drop predictable across thirteen packs.
  • BMS in the upper bay. Reachable without pulling the packs, and away from the heat at the base of the cabinet.
  • Air path on the cooled build. Intake at the base, exhaust through the louvred upper doors. Do not place it against a wall without the clearance in our installation drawing, or it will derate on a hot day.
  • Liquid build uses glycol. A 50 percent ethylene glycol mix, so it survives a site that sees occasional frost without a heater.

CERTIFICATION

What the paperwork covers

UN 38.3

Transport test summary for the cells and packs. Your forwarder will ask for this before accepting the shipment.

CE & RoHS

Issued per build. A report for the air-cooled cabinet does not cover the liquid-cooled one, so ask for the number that matches what you are buying.

ISO 9001

Plant level, covering the Hangzhou site. Usually enough for EPC prequalification, not for product approval.

If your authority asks for IEC 62619 or IEC 62933, say so at enquiry. Those are the standards most commercial storage approvals lean on, and we will tell you exactly which documents exist for this build rather than promising a certificate we have not seen. Getting that answer before the deposit is worth more than getting it after.

TYPICAL CONFIGURATIONS

Three sites this cabinet fits

Sizing still depends on your tariff and load profile. These are the shapes we see most often, not promises about savings.

HNBESS battery cabinet installed on a concrete pad beside a cold store

A cabinet on an outdoor pad, cabled into the building distribution board. This is the layout most cold stores use.

COLD STORE, PEAK SHAVING

261 kWh / 125 kW air

Compressors drive a sharp morning peak. The cabinet covers it and recharges at night. At 90% depth of discharge the daily throughput is about 470 kWh across two cycles.

Indoor plant room, suppressed at order

FUEL STATION, OUTDOOR

261 kWh / 125 kW liquid

No plant room, so the unit sits on a pad behind the canopy. Ambient passes 45 degrees in summer, and the fire authority wants factory-fitted suppression.

Outdoor pad, 1,000 × 1,300 mm footprint

FACTORY, PV COUPLED

261 kWh / 125 kW air + 250 kW PV

Roof array lands directly on the cabinet's eight trackers, no separate PV inverter. The battery absorbs the midday surplus and releases it into the evening shift.

Shaded plant room, 8 MPPT

SITE AND BUYING

What the site and the order need

FoundationA level concrete pad. For the air-cooled cabinet plan for 2.1 t over a 1.26 by 1.42 m footprint, roughly 1.2 t per square metre. Liquid is about 2 t per square metre. Get a structural check above ground floor.
AccessThe air-cooled cabinet is 1,260 mm wide and fits a standard roller shutter. The liquid unit is 1,000 mm wide but 2,500 mm tall, so measure the lintel before you book delivery.
ClearanceThe air-cooled build exhausts through the upper doors. Leave the clearance in our installation drawing or it will derate on a hot day. Liquid needs access to the pump bay for service.
Minimum orderOne unit. Projects above three units are quoted individually with a shared shipping plan.
Lead time25 to 35 days after deposit. The enclosure and the fire kit are built to order, so the clock starts on payment.
ShippingSeaworthy crate, 2,100 or 2,600 kg net. Tell us the destination port at enquiry and we will quote the freight separately from the goods.
DocumentsFoundation drawing, cable schedule, grid interconnection parameters and the fire datasheet go out with the order confirmation.
HS code8507.60 for the battery. Confirm with your broker, since some destinations classify a complete cabinet differently from a bare pack.

QUESTIONS

Six things buyers ask about this cabinet

Air cooled or liquid cooled, which should I order?

Air if the cabinet sits in a shaded plant room, the ambient stays under 40 degrees, and you want PV on the same unit. Liquid if it sits outdoors, the summer passes 45 degrees, or the fire authority wants suppression fitted at the factory rather than specified by the buyer. On a cold store with an indoor plant room, air plus ordered suppression is usually the cheaper route to the same approval.

Does the cabinet include the PCS?

Yes. Unlike our container family, this cabinet ships complete with the PCS inside and delivers three-phase 380V at its terminals. The price you are quoted is for a machine that runs, not for a battery that still needs an inverter on site.

Can I connect PV directly?

On the air-cooled builds, yes. The 125 kW build has 8 MPPT trackers and accepts up to 250 kW of panels at up to 1,000V. The 100 kW build has 10 trackers and 200 kW. The liquid-cooled build is documented without PV figures, so if you need PV on that one, ask before you design around it.

Will it pass fire approval?

The liquid unit arrives with perfluorohexanone, aerosol and water suppression plus temperature, smoke and CO detection. The air unit needs suppression specified at order. Neither guarantees local approval, which is a site process. What we can do is send the fire datasheet and cell test reports before you commit, so your consultant can check them against local code first.

What foundation does it need?

A level concrete pad sized to the footprint plus the clearance in the drawing. The air-cooled cabinet puts about 1.2 t per square metre on the slab, the liquid one about 2 t. Above ground floor, or on any slab you cannot confirm, get a structural check. A cabinet that settles unevenly will stress the pack racks.

How long from order to delivery?

25 to 35 days after the deposit clears, plus sea freight. For a project with a fixed commissioning date, tell us the date at enquiry and we will confirm in writing whether it is achievable. If it is not, we will say so before you sign rather than after.

QUICK QUOTE

Send the peak load and the site conditions

Tell us the peak demand in kW, the daily consumption in kWh, the summer ambient and whether the unit sits indoors or out. That is enough to pick between the three builds and give you a price. Usually within 12 hours on a working day.